Accessibility - Wheelchair Van Access

Accessibility - Wheelchair Van Access on the Home Building Timeline in the diagram beginning at PP-19

   
AdVanced Preliminary

AdVanced Preliminary on the Home Building Timeline at DD-23, EE-25

   
Affordable

Affordable : Articles concerning effectiVe cost control for building of new homes, additions, remodeling, and renoVations are within the Home Building Timeline category AFFORDABLE.

   
Aging In Place

Aging In Place on the Home Building Timeline at V-23, X-26 and FF-22; and in the category  Aging-In-Place

   
Air Conditioning and Heating Equipment - Finished Installation

Air Conditioning and Heating Equipment - Finished Installation on the Home Building Timeline at V-8

   
Aluminum Corrosion

Aluminum Corrosion In HomeBuildingTimeline.com within the article AVoid Aluminum Failure by the Sea

Also see Early Specifications & Material Selection on the Home Building Timeline at EE-22, FF-25

Article: Aluminum Failure by the Sea

   
Andy Bozeman

Andy Bozeman - The results of the work of Andy Bozeman is all oVer Home Building Timeline because he wrote it and drew all the illustrations. Good job, Andy !

   
Appraisal for Existing House with Planned Changes, Prior to Purchase

Appraisal for Existing House with Planned Changes, Prior to Purchase on the Home Building Timeline at K-11

It's expensiVe to pre-appraise eVery house you might consider for purchase, so don't. But, as soon as all candidate properties are narrowed to only one, it could be Very expedient to ascertain both present and future Value, based on any planned renoVations.

A little money spent now to gain critical knowledge, eVen if it leads to cancelling the project and purchase, could saVe a fortune, as well as aVert years of potential heartache.

   
Appraisal for RenoVation, Preliminary

Appraisal for RenoVation, Preliminary on the Home Building Timeline at JJ-9

   
ApproVal

ApproVal on the Home Building Timeline at JJ-15

   
ApproVal, Early Preliminary

ApproVal, Early Preliminary on the Home Building Timeline at EE-21, EE-22

   
ApproVal, Final Document Preparation for

ApproVal, Final Document Preparation for : on the Home Building at FF-21, FF-22

   
Architectural ReView Committee Plan Submission

Architectural ReView Committee Plan Submission on the Home Building Timeline at II-17

   
Area : Square feet Vs Square Meters

AREA - Home Building Timeline refers to area calculations based on Square Feet because the primary target-readers liVe in the United States. Square feet for Area and Measurement is a component of the Imperial Measurement System.

Almost all the rest of the world uses the Metric Measurement System, a far superior method.  Metric measurements are easier and faster to determine, and Vastly reduce the probability or error.

   
Area, LiVing

Area, LiVing is part of the definition for Interior Area on the Home Building Timeline at R-25.

LiVing Area includes all walls needed to enclose the heated and cooled area of a house, whereas Interior Area is only the empty space in any giVen room or group of rooms.

   
Area, Volume

Area, Volume on the Home Building Timeline at R-25

   
As-Built Measurement Verification

As-Built Measure Verification on the Home Building Timeline at DD-8.

This note's instructions are located at CC-9

   
Attic & Roof PassiVe Vents - Order for DeliVery

Attic & Roof PassiVe Vents - Order for DeliVery on the Home Building Timeline at W-19

   
AValanche

AValanche on the Home Building Timeline at Z-8

   


 
Balloon Mortgage

Balloon Mortgage : At the end of the initial phase of a sub-prime mortgage, in which monthly payments are kept artificially low, payments expand suddenly, oVernight or "balloon" to many times the original payment amount. Those people who borrow such a Balloon Mortgage find themselVes unable to make the Very high payments each month, and are forced into foreclosure. Be here warned to NEVER become part of such a financial arrangement.

See GHOST BUBBLE, an Amazon Kindle eBook

   
Basement ExcaVation

Basement ExcaVation on the Home Building Timeline at W-1

   
BEADS Keystone

BEADS Keystone on the Home Building Timeline described, beginning at H-10, implemented at L-10.

This contains the MOST CRITICAL questions, which must be asked as if the entire BEADS Keystone is one step.

This is the most critical aspect of site selection, and construction. The BEADS Keystone is applicable throughout the entire process of home planning, building, remodeling, flipping, and selling.

Further, the BEADS Keystone extends into the future, after moVe-in, and affects eVery aspect of home maintenance, comfortable liVing, and peaceful enjoyment.

   
Beam Strength

Beam Strength on the Home Building Timeline at V-16

   
Bearing Soil Verification

Bearing Soil Verification on the Home Building Timeline at II-22

   
Bid ReView

Bid ReView on the Home Building Timeline at GG-19

   
Blow Out PreVention for Foundation Curtain Walls

Blow Out PreVention for Foundation Curtain Walls on the Home Building Timeline at Q-12

   
BOOK - If I'd Known That Was Going to Happen When I Built My House, I Might'Ve Gone Camping Instead

BOOK - If I'd Known That Was Going to Happen When I Built My House, I Might'Ve Gone Camping Instead by Andy Bozeman on the Home Building Timeline at P-3

   
Borrowing NEVERS

Borrowing NEVERS on the Home Building Timeline at K-6

   
Boundary Line Verification

Boundary Line Verification on the Home Building timeline at HH-8

   
Brick and Mortar - Order for DeliVery

Brick and Mortar - Order for DeliVery on the Home Building Timeline at EE-13

   
Building Code Vs Plat Restrictions

Building Code Vs Plat Restrictions on the Home Building timeline at O-22

   
Building Line

Building Line on the HomeBuildingTimeline within the diagram centered at D-3 illustrating many types of Building Lines. Also see the Article SITE LINES, which begins at F-6. Also B-9.

 

 

Also see BEADS Keystone at I-11

 

NO-BUILD ZONES are designated on a property surVey/plat by BUILDING LINES. No construction may occur in the space between any Building Line and any associated property line.

Building Lines affect the Front, Sides, and Rear of the property; plus Easements, and Right of Ways. Sometimes eVen paVement and landscaping can be controlled by Building Lines.

   
Building Line Verification

Building Line Verification on the Home Building timeline at HH-8

   
Building Lines and UncoVered Decks, Patios, and Terraces

Building Lines and UncoVered Decks, Patios, and Terraces at A-1 on the Home Building Timeline

   
Building Restriction Line

Building Restriction Lines on the HomeBuildingTimeline at Grid D-3 is the center of a diagram illustrating many types.

NO-BUILD ZONES are designated on a property surVey/plat by BUILDING RESTRICTION LINES. No construction may occur in the space between any Building Restriction Line and any associated property line.

Restriction Lines affect the Front, Sides, and Rear of the property; plus Easements, and Right of Ways. Sometimes eVen paVement and landscaping can be controlled by Restriction Lines.

   
Building Setback Line

Building Setback Line on the Home Building Timeline within the diagram centered at D-3. Also see SITE LINES at F-6.

NO-BUILD ZONES are designated on a property surVey/plat by Building Setback Lines. No construction may occur in the space between any Building Setback Line and any associated property line.

Building Setback Lines affect the Front, Sides, and Rear of the property; plus Easements, and Right of Ways. Sometimes eVen paVement and landscaping can be controlled by Building Lines.

   
Buried Infrastructure

 Buried Infrastructure and Utilities Location Verification on the Home Building Timeline at K-14, O-23

   
Buried Utilities Location Verification

Buried Utilities Location Verification on the Home Building Timeline at K-14, O-23

   


 
Cabinet Measurement Verification

Cabinet Measurement Verification on the Home Building Timeline at DD-8

   
CantileVer Deck Addition

CantileVer Deck Addition on the Home Building Timeline at X-20

   
Carport Size

Carport Size on the Home Building Timeline at I-9, NN-7, OO-7, PP-7, QQ-7, RR-7, SS-7, UU-7, VV-7, WW-7

   
CaVe-in PreVention

CaVe-in PreVention on the Home Building Timeline at W-3

   
CaVe-In Protection

CaVe-In Protection on the Home Building Timeline at V-4

   
Ceiling Height Verification

Ceiling Height Verification on the Home Building Timeline at Q-7

   
Central Vacuum Tubing Installation

Central Vacuum Tubing Installation on the Home Building Timeline at DD-15

   
Cleanup, Routine

Cleanup, Routine on the Home Building Timeline at EVERY step to reduce fire hazards, control drainage issues, manage dust control, and preVent ground-water poisoning.

 

 

ROUTINE = DAILY

At eVery step, and at the conclusion of eVery process, assure that the entire homesite is neat and clean. This dramatically reduces any potential FIRE HAZARD, as well as reducing the Accumulation and Damming of debris and trash resulting from Drainage.

 

 

Pick up tossed-away board ends. Collect them together for  mulching, or to be carried off-site. DO NOT BURN!!!!

Police the entire site for lunch-garbage, including sacks, wrappers, bottles, cans, and cartons.

Pickup cigar and cigarette butts.  

 

 

NEVER allow, or tolerate, the tossing of any debris, or trash, into footings and foundation works. After the material decays, hollows are left, which will weaken the foundation, and probably lead to foundation failure.

Sweep the floors and rake the grounds, eVery day. Then, BAG the TRASH.

Search for the topic CLEANUP within HomeBuildingTimeline.com.

   
Clothing, ProtectiVe

Clothing, ProtectiVe on the Home Building Timeline at JJ-6

   
Collapse Protection

Collapse Protection on the Home Building Timeline at V-4

   
Color of Light - LiVing With It

Color of Light - LiVing With It on the Home Building Timeline at AA-12

   
Common Wall

Common Wall inside HomeBuildingTimeline.com within the article Townhome RenoVation Includes Neighbor's Exterior Common Wall

   
Common-Wall

Common-Wall :

A wall between separate dwelling units, like condominiums, and townhomes.

Also see the Home Building Timeline article, Townhouse RenoVation Includes Neighbor's Exterior Walls.

   
Compaction Test and Assurance

Compaction Test and Assurance on the Home Building Timeline at V-3

   
Concrete Block and Mortar - Order for DeliVery

Concrete Block and Mortar - Order for DeliVery on the Home Building Timeline at EE-13

   
Connection Inspection, Duct and Vent

Connection Inspection, Duct and Vent on the Home Building Timeline at EE-16

   
ConserVation Easement

ConserVation Easement on the Home Building Timeline at G-1, FF-4

   
conVerging
   
ConVerging Projected Waterfront Property Lines

ConVerging Projected Waterfront Property & Set-Back Lines on the Home Building Timeline in the diagram beginning at A-18

   
ConVerging Property Lines and Debris Disposal

ConVerging Property Lines and Debris Disposal on the Home Building Timeline at JJ-1

   
ConVert Construction Loan to Permanent Mortgage

ConVert Construction Loan to Permanent Mortgage on the Home Building Timeline at Z-13

   
Corners of Structures Verification

Corners of Structures Verification on the Home Building timeline at HH-8

   
Cost - EnVironmental Impact Fees

Cost - EnVironmental Impact Fees on the Home Building Timeline at L-14

   
Cost Vs Value

Cost Vs Value on the Home Building Timeline at H-8

   
Cost, Utility SerVices

Cost, Utility SerVices on the Home building Timeline at L-9

   
Costs of Home Ownership - OBVIOUS

Costs of Home Ownership - OBVIOUS on the Home Building Timeline at L-7

   
Costs of Home Ownership - OVERLOOKED

Costs of Home Ownership - OVERLOOKED on the Home Building Timeline at L-8

   
Counter-Shoring

Counter-Shoring on the Home Building Timeline at V-4

   
Countertop Measurement Verification

Countertop Measurement Verification on the Home Building Timeline at DD-8

   
Countertops - Order for DeliVery

Countertops, Place Order for: on the Home Building Timeline at DD-8

   
CoVenants (Plat Restrictions)

CoVenants (Plat Restrictions) on the Home Building Timeline at F-9,  within BEADS Keystone at H-10, and SITE HAZARDS at I-19, and M-16

   
Crawlspace ExcaVation

Crawlspace ExcaVation on the Home Building Timeline at T-3

   
CulVert Installation Permit

CulVert Installation Permit on the Home Building Timeline at II-11

   
Curtain Wall Blow Out PreVention

Curtain Wall Blow Out PreVention on the Home Building Timeline at Q-12

   


 
X-Decayed Structure EVidence

Decayed Structure EVidence on the Home Building Timeline at Q-14

   
X-Deck

Deck on the Home Building Timeline at A-1, A-2, DD-9, V-19

   
X-Door Clearance - Vehicle

Door Clearance - Vehicle on the Home Building Timeline at VV-14

   
X-Door Hardware RemoVal During Painting

Door Hardware RemoVal During Painting on the Home Building Timeline at W-5

   
X-Doors DeliVered

Doors DeliVered on the Home Building Timeline at AA-18

   
X-Doors, Order for DeliVery

Doors, Order for DeliVery on the Home Building Timeline at R-15

   
X-Drainage

Drainage - on the Home Building Timeline at EVERY step.

At eVery step, and in eVery process, assure that the drainage of all potential water, whether from rain, snow, broken pipes, or yard sprinklers, is fully controlled to preVent erosion, softening of bearing soil, and undesirable pooling and ponding under, around and inside the house, as well as across the property.

Search for the topic DRAINAGE within HomeBuildingTimeline.com.

   
X-Drainage, PreserVation of Existing

Drainage, PreserVation of Existing on the Home Building Timeline at II-22, II-23

   
X-Drainage, Storm, ExcaVation

Drainage, Storm, ExcaVation on the Home Building Timeline at Y-2

   
X-Drainage, Trench and Pit

Drainage, Trench and Pit on the Home Building Timeline within note centered at V-4

   
X-DriVeway

DriVeway on the Home Building Timeline at F-2

   
X-DriVeway Anatomy

DriVeway Anatomy on the Home Building Timeline beginning at A-22

   
X-DriVeway Concrete Forms

DriVeway Concrete Forms on the Home Building Timeline at BB-6

   
X-DriVeway Concrete Placement

DriVeway Concrete Placement on the Home Building Timeline at AA-6

   
X-DriVeway, Asphalt

DriVeway, Asphalt on the Home Building Timeline at C-23

   
X-DriVeway, Clay-GraVel

DriVeway, Clay-GraVel on the Home Building Timeline at C-23

   
X-DriVeway, Concrete

DriVeway, Concrete on the Home Building Timeline at C-23

   
X-DriVeway, Crushed Stone

DriVeway, Crushed Stone on the Home Building Timeline at C-23

   
X-DriVeway, Natural Earth

DriVeway, Natural Earth on the Home Building Timeline at C-23

   
X-DriVeway, Permanent, Rough-in

DriVeway, Permanent, Rough-in on the Home Building Timeline at V-3

   
X-DriVeway, Temporary - Designate Location

DriVeway, Temporary - Designate Location on the Home Building Timeline at II-7

   
X-DriVeway, Temporary - for Construction Vehicles and Equipment

DriVeway, Temporary - for Construction Vehicles and Equipment on the Home Building Timeline at II-6

   
X-DriVeway, Temporary, ExcaVation

DriVeway, Temporary, ExcaVation on the Home Building Timeline at V-2

   
X-Duct and Vent Connection Inspection

Duct and Vent Connection Inspection on the Home Building Timeline at EE-16

   
X-Ductwork - Finished Installation

Ductwork - Finished Installation on the Home Building Timeline at V-8

   


 
Easement

Easement on the Home Building Timeline at C-4, H-4, G-10, M-19; also throughout the diagram centered at D-3; also see BEADS KEYSTONE,

 A NO-BUILD-ZONE, an Easement is an area of property used to preserVe aspects of infrastructure, usually for multiple properties. No construction is eVer allowed within an easement. No obstruction, such as fallen trees or the build up of discarded yard trimmings, etc., are eVer allowed to remain, and must be remoVed immediately.

The most common easement is a Drainage Easement, which directs the flow of rain water in a manner to preVent flooding of or water damage to properties affected by the easement.

   
Easement, ConserVation

Easement, ConserVation on the Home Building Timeline at D-6, G-1, FF-4

   
Easement, PriVate Utility & Drainage (PUDE)

Easement, PriVate Utility & Drainage (PUDE) on the Home Building Timeline at B-6

   
Electric SerVice Installation

Electric SerVice Installation on the Home Building Timeline at BB-2

   
Electrical Inspection

Electrical Inspection on the Home Building Timeline at V-8

   
Electrical, Finish Installation

Electrical, Finish Installation on the Home Building Timeline at V-8

   
Electrical, Label All Circuits

Electrical, Label All Circuits on the Home Building Timeline at V-8

There's nothing so frustrating or time wasting as attempting to determine which circuit just tripped off.

Right now, while the electrician is still on-site, label each circuit, specifically, for what it powers, whether a certain bedroom's outlets, or the refrigerator, or the AC unit, etc.

There will neVer be a better time.

   
EleVator Pit & Related Sump Pit

EleVator Pit & Related Sump Pit on the Home Building Timeline at W-3

   
Engineered Clay Pad for Flat Ground

Engineered Clay Pad for Flat Ground - on the Home Building Timeline at V-1.

   
EnVironmental Impact Fees

EnVironmental Impact Fees on the Home Building Timeline at L-14

   
Erosion PreVention Measures

Erosion PreVention Measures on the Home Building Timeline at RR-1

   
EVidence of Chronic Pest Infestation

EVidence of Chronic Pest Infestation on the Home Building Timeline at Q-15

   
EVidence of Decayed Structure

EVidence of Decayed Structure on the Home Building Timeline at Q-14

   
ExcaVate Footings

ExcaVate Footings on the Home Building Timeline at T-4

   
ExcaVate for Basement

ExcaVate for Basement - on the Home Building Timeline at W-1

   
ExcaVate for Crawlspace

ExcaVate for Crawlspace on the Home Building Timeline at T-3

   
ExcaVate for Foundation

ExcaVate for Foundation on the Home Building Timeline at T-4

   
ExcaVation Phase

ExcaVation Phase on the Home Building Timeline at Z-2

   
Extent of Structure

Extent of Structure on the Home Building Timeline.at G-7, H-13, S-25, Q-26, R-26, S-26, T-26

In the BEADS KEYSTONE at H-13

 

Diagrammed at at S-25, T-26

 

ALLOWED EXTENT OF STRUCTURES :The applied ‘extent’ of a structure is the part allowed to touch, but not cross a building line. Rules Vary. The extent considered might be the edge of walls, footings, any oVerhangs, decks, patios, stoops, steps, eaVes, arbors, and more. CHECK CAREFULLY.

   
Exterior Surfacing & trim Materials - Order for DeliVery

Exterior Surfacing & trim Materials - Order for DeliVery on the Home Building Timeline at W-19

   


 
Face Plate RemoVal During Painting

Face Plate RemoVal During Painting on the Home Building Timeline at X-6

   
Failure EVidence, Foundation

Failure EVidence, Foundation on the Home Building Timeline at P-14

   
Fall Protection

Fall Protection on the Home Building Timeline at V-4

   
Fall Protection Installation

Fall Protection Installation on the Home Building Timeline at V-19

   
Fire PreVention Measures

Fire PreVention Measures on the Home Building Timeline at CC-3

   
Fire PreVention Vehicle & Equipment Access

Fire PreVention Vehicle & Equipment Access on the Home building Timeline at CC-3, HH-6

   
Fire SurViVal

Fire SurViVal on the Home Building Timeline at JJ-22

   
Floor Framing Installation

Floor Framing Installation on the Home Building Timeline at V-18, diagrammed at R-19

   
Footings, ExcaVate For

Footings, ExcaVate For on the Home Building Timeline at T-4

   
Form Work, RemoVe

Form Work, RemoVe on the Home Building Timeline at R-15

   
Form, DriVeway Concrete

 Form, DriVeway Concrete  on the Home Building Timeline at BB-6

   
Foundation Blow Out PreVention

Foundation Blow Out PreVention on the Home Building Timeline at Q-12

   
Foundation Failure EVidence

Foundation Failure EVidence on the Home Building Timeline at P-14

   
Foundation, ExcaVate For

Foundation, ExcaVate For on the Home Building Timeline at T-4

   
Framing Materials - Order for DeliVery

Framing Materials - Order for DeliVery on the Home Building Timeline at Q-8

Includes Floors, walls, ceilings, and roof

   
Framing, Begin for Walls, Ceiling, Roof

Framing, Begin for Walls, Ceiling, Roof on the Home Building Timeline at V-19

   
Front Building Line

Front Building Line on the HomeBuildingTimeline at E4 and E5.

Also see BEADS Keystone

The FRONT BUILDING LINE, also know as the front setback line, marks the point on any giVen property that is the nearest to the Front property line where a structure may be built.

MEASURING THE FRONT BUILDING LINE : The Front Building Line cannot measured from the street. the curb, the edge of the paVement, or the edge of the road. It must be measured from the property line designated as the Front of the lot. If you are unable to determine the exact location of the Front Property Line, then find a professional who can offer assistance.

 

   
Front Setback Line

Front Setback Line on the Home Building Timeline at B-9, C-9, E4, E5.

The FRONT SETBACK LINE, also known as the front building line, marks the point on any giVen property that is the nearest to the Front property line where a structure may be built.

MEASURING THE FRONT Setback LINE : The Front Setback Line is NOT measured from the street. the curb, the edge of the paVement, or the edge of the road. It must be measured from the property line designated as the Front of the lot. If you are unable to determine the exact location of the Front Setback Line, then find a professional who can offer assistance.

   
Furnishings RemoVal for RenoVation

Furnishings RemoVal for RenoVation on the Home Building Timeline at JJ-6

   


 
Garage Size

Garage Size on the Home Building Timeline at I-9, NN-9, OO-9, PP-9, QQ-9, RR-9, SS-8, UU-9, VV-9, WW-9, X-26

   
Gazebo and PaVilion

Gazebo and PaVilion on the Home Building Timeline at A-2

   
Green Building Tax IncentiVes

Green Building Tax IncentiVes on the Home Building Timeline at II-16

   
Green Building Verifier

 Green Verifier on the Home Building Timeline at EE-11, II-7, U-10, II-16, V-19

   
Green Building Verifier - Capillary Barrier

Green Building Verifier - Capillary Barrier on the Home Building Timeline at Q-8

   
Green Building Verifier - Head Flashing

Green Building Verifier - Head Flashing on the Home Building Timeline at BB-17

   
Ground CoVerage

Ground CoVerage on the Home Building Timeline at CC-25

   
Guesstimate

Guesstimate on the Home Building Timeline at H-9

This is a slang reference to the attempt to estimate the final construction cost too early in the process, when there's not enough information aVailable. It is a GUESS at an ESTIMATE.

   


 
Happily EVer After

Happily EVer After on the Home Building Timeline at Z-12

While not an illustrated step on the Timeline, this is the ultimate goal at the end.

   
Heating and Air Conditioning Equipment - Finished Installation

Heating and Air Conditioning Equipment - Finished Installation on the Home Building Timeline at V-8

   
Hillside, OVer-Cut

Hillside, OVer-Cut on the Home Building Timeline at UU-1, UU-2

   
HVAC heating Ventilation air conditioning

HVAC (heating, Ventilation, air conditioning) on the Home Building Timeline at W-26 and DD-16

   


 
Infestation, EVidence of Chronic Pests

Infestation, EVidence of Chronic Pests on the Home Building Timeline at Q-15

   
Inspection, Duct and Vent Connection

Inspection,  Duct and Vent Connection on the Home Building Timeline at EE-16

   
Inspection, Electrical

Inspection, Electrical on the Home Building Timeline at V-8

   
Installation, Finished, Mechanical Equipment

Installation, Finished, Mechanical Equipment on the Home Building Timeline at V-8

   
Insurance CoVerage Verification

Insurance CoVerage Verification on the Home Building Timeline at Y-14

   
Insurance CoVerage, Increase Construction Phase

Insurance CoVerage - Increase for Construction Phase on the Home Building Timeline at BB-18

   


 
Land

Land on the Home Building Timeline at L-12

Category - Land & Lot

Article : NeVer Fall In LoVe With Dirt

   
Landscape Details and Plantings Installation

Landscape Details and Plantings Installation on the Home Building Timeline at V-14

   
Landscaping : 'LiVe' Plant Barriers & Wrapping for Protection

Landscaping : 'LiVe' Plant Barriers & Wrapping for Protection on the Home Building Timeline at II-7

   
Landscaping : LiVe-Plant Staging Areas

Landscaping : LiVe-Plant Staging Areas on the Home Building Timeline at HH-7

   
Light Fixture DeliVery to Site

Light Fixture DeliVery to Site on the Home Building Timeline at V-7

   
Light Fixture RemoVal for RenoVation

Light Fixture RemoVal for RenoVation on the Home Building Timeline at KK-7

   
LiVestock

LiVestock on the Home Building Timeline at Y-26, Z-26

   
LiVing Area

LiVing Area is part of the definition for Interior Area on the Home Building Timeline at R-25.

LiVing Area includes all walls needed to enclose the heated and cooled area of a house, whereas Interior Area is only the empty space in any giVen room or group of rooms.

   
Look of the Plan and House

Look of the Plan and House on the Home Building Timeline at W-24, discussed at V-25, W-25

   


 
Markers, Warning

Markers, Warning on the Home Building Timeline at V-4

   
Masonry Materials - Order for DeliVery

Masonry Materials - Order for DeliVery on the Home Building Timeline at EE-13

   
Mechanical - Definition

Mechanical - Definition : Refers to all equipment related to the infrastructure of a house for the purpose of moVing air and fluids. This includes HVAC (heating, Ventilation, and air conditioning) connections, duct-work, and equipment, such as air handlers, furnaces, compressors, and humidifier/dehumidifier units. It also includes all plumbing pipes, fittings, and ValVes.

   
Money, SaVing

Money, SaVing on the Home Building Timeline at K-6

   
Monkey See Monkey Do (also see MSMD)

Monkey See Monkey Do : An actual but wrong method of construction-cost calculation performed by an incompetent builder who is copying other incompetent builders, none of whom has any knowledge of construction costs whatsoeVer.

   
MoVe In

MoVe In on the Home Building Timeline at Z-12

   
MoVing Around In The House

MoVing Around In The House on the Home Building Timeline at V-24, discussed at W-23

   


 
OVer-Cutting a Hillside

OVer-Cutting a Hillside on the Home Building Timeline at Y-3, and in the diagram beginning at SS-1 

   
OVerhead Power Line Location Verification

OVerhead Power Line Location Verification on the Home Building Timeline at O-23

   
OVerhead Utility Wiring

OVerhead Utility Wiring on the Home Building Timeline at I-3

   


 
P.U.D.E. - PriVate Utility & Drainage Easement

P.U.D.E. : PriVate Utility & Drainage  Easement on the Home Building Timeline at B-6

   
Paint - Final Coat

Paint - Final Coat on the Home Building Timeline at V-7

   
Paint RemoVal, Old

Paint RemoVal, Old on the Home Building Timeline at V-5

   
Parking - Vehicle - Indoor Clearances

Parking - Vehicle - Indoor Clearances on the Home Building Timeline within the diagram beginning at OO-10

   
Parking Area, Permanent, Rough-in

Parking Area, Permanent, Rough-in on the Home Building Timeline at V-3

   
Parking Area, Temporary, ExcaVation

Parking Area, Temporary, ExcaVation on the Home Building Timeline at V-2

   
PaVilion

PaVilion on the Home Building Timeline at A-2, F-11

   
Pay Off ALL Outstanding Bills, Charges, and InVoices

Pay Off ALL Outstanding Bills, Charges, and InVoices on the Home Building Timeline at Y-14

   
Pests, EVidence of Chronic Infestation

Pests, EVidence of Chronic Infestation on the Home Building Timeline at Q-15

   
Plan ReView

Plan ReView on the Home Building Timeline at II-18, described at MM-16

   
Plan Types and Site Suitability

Plan Types and Site Suitability on the Home Building Timeline at U-24, discussed at V-25

   
Plan Verification for Equipment Spaces, Duct, Electrical, Stairs

Plan Verification for Equipment Spaces, Duct, Electrical, Stairs on the Home Building Timeline at U-18

   
Plan Verification for ExcaVation

Plan Verification for ExcaVation on the Home Building Timeline at Z-2

   
Plantings and Landscape Details Installation

Plantings and Landscape Details Installation on the Home Building Timeline at V-14

   
Plat Restrictions Vs Building Code

Plat Restrictions Vs Building Code on the Home Building timeline at O-22

   
Ponding PreVention

Ponding PreVention on the Home Building Timeline at T-4

   
Porch Size, CoVered Area

Porch Size, CoVered Area on the Home Building Timeline at I-9

   
Power Line Location Verification, OVerhead

Power Line Location Verification, OVerhead  on the Home Building Timeline at O-23

   
Power SerVice Installation

Power SerVice Installation on the Home Building Timeline at BB-2

   
Power Vents - Order for DeliVery

Power Vents - Order for DeliVery on the Home Building Timeline at W-19

   
Preliminary, AdVanced

Preliminary, AdVanced on the Home Building Timeline at DD-23, discussed at EE-25

   
PriVate Road / Street Status Verification

PriVate Road / Street Status Verification on the Home Building Timeline at M-20

   
Property Line Verification

Property Line Verification on the Home Building timeline at HH-8

   
Propping, Shoring, Trench

Propping, Shoring, Trench on the Home Building Timeline at V-4

   
Protection for LiVe Plants

Protection for LiVe Plants on the Home Building Timeline at II-7

   
ProtectiVe CoVers

ProtectiVe CoVers on the Home Building Timeline at EE-13

   


 
Radon Venting Diagram

Radon Venting on the Home Building Timeline at  R-6 T-6

   
Radon Venting Rough In

Radon Venting Rough In : on the Home Building Timeline at R-6

   
Radon Venting Top Out

Radon Venting Top Out on the Home Building Timeline at EE-15

   
Radon Venting, Crawlspace Pipe Installation for

Radon Venting, Crawlspace Pipe Installation for : on the Home Building Timeline at T-18

   
Recreational Vehicle (RV)

Recreational Vehicle (RV) on the Home Building Timeline at F-11, within the diagram centered at SS-14

   
RestrictiVe CoVenants

RestrictiVe CoVenants on the Home Building Timeline at M-19

   
Right-of-Way V> V> V> V> V>Right of Way on the Home Building Timeline at E-4, E-5, also within the on-timeline article, SITE LINES at F-6. Also diagrammed at B-10, C-10, D-10, B-11, C-11, D-11, A-15, D-15, A-16, D-16V>

A Right-of-Way (ROW) for a street, road, or highway is a special parcel of land. A road ROW sits beside and between other parcels of property. Some examples are streets, interstate highways, railroad tracks, gas lines, and power lines.

A Right-of-Way for utilities is a special type of easement, and may pass through a priVately owned parcel of land. In such a case, the landowner still possesses the land, but is not allowed to eVer build within the ROW. Examples are gas pipelines, powerlines, and other utilities like cable teleVision and telephone; and driVeways allowing one owner to cross another owner's land.

   
Roof - NEVER New OVer Old

Roof - NEVER New OVer Old on the Home Building Timeline at CC-19

   
Roof Drainage Issues, Altered

Roof Drainage Issues, Altered on the Home Building Timeline at V-19, U-20, V-20

   
Roof Framing - Begin Installation

Roof Framing - Begin Installation on the Home Building Timeline at V-20

   
Roof Materials: Order for DeliVery

Roof Materials : Order for DeliVery on the Home building Timeline at EE-13

   
Roof Plane Intersection and Rainwater Run Off

Roof Plane Intersection and Rainwater Run Off on the Home Building Timeline at V-20

   
Roof Surface Material Verification

Roof Surface Material Verification on the Home Building Timeline at AA-19

   
Roof Surface Materials : Order for DeliVery

Roof Surface Materials : Order for DeliVery on the Home building Timeline at EE-13

   
Roofing Materials - DeliVered

Roofing Materials - DeliVered on the Home Building Timeline at AA-19

   
Room Size Vs Plan Dimension

Room Size Vs Plan Dimension on the Home Building Timeline at T-21, DD-26

   
ROW or Right of Way

 

ROW or Right of Way on the Home Building Timeline at E-4, E-5, also within the article, SITE LINES at F-6. Also diagrammed at B-10, C-10, D-10, B-11, C-11, D-11, A-15, D-15, A-16, D-16

A Right-of-Way (ROW) for a street, road, or highway is a special parcel of land. A road ROW sits beside and between other parcels of property. Some examples are streets, interstate highways, railroad tracks, gas lines, and power lines.

 A Right-of-Way for utilities is a special type of easement, and may pass through a priVately owned parcel of land. In such a case the landowner still possesses the land, but is not allowed to eVer build within the ROW. Examples are gas pipelines, powerlines, and other utilities like cable teleVision and telephone; and driVeways allowing one owner to cross another owner's land.

   
Rule Variations

Rule Variations on the Home Building Timeline at N-20

   
RV (Recreational Vehicle)

 RV (Recreational Vehicle) on the Home Building Timeline at F-11, within the diagram centered at SS-14

   


 
Safes & Vaults

Safes & Vaults on the Home Building Timeline at AA-22

   
Septic Tank and Leach Field Location Verification

Septic Tank and Leach Field Location Verification on the Home Building Timeline at HH-22

   
Setback Line

SETBACK LINE on the Home Building Timeline in the diagram centered at A-18, D-3, B-7, B-9, C-7, C-9, D-7. 

 

A SETBACK line is measured from a property line, whether front, side, or rear.

Hire a professional surVeyor to help find the property line, first, then the setback lines.

   
Shoring

Shoring on the Home Building Timeline at SS-5V-4

   
Shoring for Blow Out PreVention

Shoring for Blow Out PreVention on the Home Building Timeline at Q-12

   
Shoring, Counter

Shoring, Counter on the Home Building Timeline at V-4

This is not about a kitchen or bath counter. This is about balancing force to keep a wall from collapsing, during renoVation,or demolition.

   
Sill Plates on Top of Masonry Walls, Check - Square and LeVel

Sill Plates on Top of Masonry Walls, Check - Square and LeVel on the Home Building Timeline at Q-14

   
Silt Fence Inspection and Repair

Silt Fence Inspection and Repair on the Home Building Timeline at R-15, S-5, U-3, V-14, BB-7, CC-17

   
Silt Fence Installation

 

Silt Fence Installation on the Home Building Timeline at II-8, Y-2

 

 

No physical materail is allowed to cross oVer any property line, whether sawdust, graVel, cement & mortar particles, lunch trash, human & animal waste, spilled paint, nails & screws, drywall bits & flakes, eVen muddy water. 

 

II-8 : Install primary silt fence for initial control of erosion and rain-water run-off from the property.

Y-2 : Install any needed additional Silt Fencing to assure full control of rain-water run-off. 

   
Site Suitability and Plan Types

Site Suitability and Plan Types on the Home Building Timeline at U-24, discussed at V-25

   
Solar HarVesting

Solar HarVesting on the Home Building Timeline at CC-26

   
Solar Rights

Solar Rights on the Home Building Timeline at I-17;  and within the topic SOLAR ENERGY INVESTMENT PROTECTION LAWS

   
Stability of EVerything

Stability of EVerything on the Home Building Timeline at grid H-16.

Part of The BEADS KEYSTONE.

   
Stair - Wall Stringer, DecoratiVe

Stair - Wall Stringer, DecoratiVe on the Home Building Timeline at MM-26

   
Stair Safety

Stair Safety on the Home Building Timeline at VV-24

   
Stair Stringer

Stair Stringer on the Home Building Timeline at NN-24, MM-26

A Structural Stringer supports the weight of the moVement on the stairs of people and possessions.

A DecoratiVe Stringer looks pretty but is non-load-bearing.

   
Stair Winder

Stair Winder on the Home Building Timeline at VV-25

   
Stone and Mortar - Order for DeliVery

Stone and Mortar - Order for DeliVery on the Home Building Timeline at EE-13

   
Stop and Think

 

Stop, and Think on the Home Building Timeline EVERYWHERE.

"Thinking" is the second least-used tactic in the planning and construction process. The first least-employed tactic is stopping to do it.

Building anything dwelling-related is a hurried, high-pressure, higher-expectations, highest-emotional-state experience. 'Reason' is replaced by anxiety; and bad decision-making follows, naturally. The cure is to giVe yourself a moment to consider options. So, stop and think.

 

Learn these phrases and use them often:

 

"This doesn't seem right. I need some time to think about it."

 

"Let's look at that more closely."

 

"How can we fix this problem?"

 

Gain the high ground in any situation by seizing the moment to stop and think.

Concerning eVery aspect of this project :

If you're unsure, stop and become certain.

If a thing is unknown to you, stop and learn about it.

When a mistake is made, by you or others, stop and find of a solution.

The key word is STOP. Don't worry if people around you are impatient. Stand firm, as you actiVely seek positiVe solutions. -AB

 

   
Storage, Garage

Storage, Garage on the Home Building Timeline at SS-9, within the Vehicle Diagrams centered on RR-13, SS-15, RR-20

   
Storm Drainage ExcaVation

Storm Drainage ExcaVation on the Home Building Timeline at Y-2

   
Storm Shelter ExcaVation

Storm Shelter ExcaVation on the Home Building Timeline at W-2

   
Structural Decay, EVidence of

Structural Decay, EVidence of : on the Home Building Timeline at Q-14

   
Sump Pit ExcaVation

Sump Pit ExcaVation on the Home Building Timeline at W-2, W-3

   
Super Genius

Super Genius

Andy Noel founder of ProSauraSystems.com is one. He created the mechanism for this Index.

Sander de Wijs (de-Veihs for Americans) owner of The Netherlands-based Degrinthorst.nl is chief of programming, and also a super genius. He writes all of the code to make HomeBuildingTimeline.com function.

   
SurVey to place House on Site

SurVey to place House on Site on the Home Building Timeline at BB-2

   
SurViVal of Possessions

SurViVal of Possessions on the Home Building Timeline at Z-23

   
SurViVal of the Occupants

SurViVal of the Occupants on the Home Building Timeline at Z-22, AA-22

   
SurViVal of the Structure

SurViVal of the Structure on the Home Building Timeline at Y-23, Z-23

   


 
Tax IncentiVes, Green Building

Tax IncentiVes, Green Building  on the Home Building Timeline at II-16

   
Telephone SerVice Installation

Telephone SerVice Installation on the Home Building Timeline at BB-2

   
Texting

Texting on the Home Building Timeline at MM-15

Inside HomeBuildingTimeline.com within the articles:

Distracted DriVing - Hidden Building Cost - No RecoVery

All Communications Must Be Direct

   
Townhome Wall Maintenance

Townhome Wall Maintenance inside HomeBuildingTimeline.com

Within the article Townhome RenoVation Includes Neighboring Exterior Common Wall

   
Trim Measurement Verification

Trim Measurement Verification on the Home Building Timeline at CC-7

   


 
Uncoupling Membrane

Uncoupling Membrane on the Home Building Timeline at V-11

   
USDA Mortgage & Plan Requirements

USDA Mortgage & Plan Requirements : The information and documentation required to qualify for, and process a USDA home loan.

The list is extensiVe and includes detailed financial information, land surVey and title-of-ownership documentation, and assurance documentation proVing compliance with all applicable building codes, energy codes, and design standards. 

   
Utility SerVices Costs

Utility SerVices Costs on the Home Building Timeline at L-9

   


 
Value

Value on the Home Building Timeline at H-8, K-10

   
Value Vs Cost

Value Vs Cost on the Home Building Timeline at H-8

   
Variance

Variance on the Home Building Timeline at P-21, HH-23

   
Vaults & Safes

Vaults & Safes on the Home Building Timeline at AA-22

   
Vegetation RemoVal Regulation Compliance

Vegetation RemoVal Regulation Compliance on the Home Building Timeline at EE-3

   
Vehicle Parking, Indoor Clearances for

Vehicle Parking, Indoor Clearances for on the Home Building Timeline within the diagram beginning at OO-10, QQ-20, TT-19, X-26

   
Vehicle, OVerhead Clearance for

Vehicle, OVerhead Clearance for : on the Home Building Timeline within the diagrams beginning at OO-10, 00-14, 00-17, 00-19,  QQ-20, TT-19

   
Vent and Duct Connection Inspection

Vent and Duct Connection Inspection on the Home Building Timeline at EE-16

   
Verify Stud Length for Ceiling Height

Verify Stud Length for Ceiling Height on the Home Building Timeline at Q-7

   


 
Warning Markers

Warning Markers on the Home Building Timeline at V-4

   
Water Rights Verification

Water Rights Verification on the Home Building Timeline at Y-2

   
Water SerVice Installation

Water SerVice Installation on the Home Building Timeline at BB-2

   
Wheelchair Van Access

Wheelchair Van Access on the Home Building Timeline in the diagram beginning at PP-19

   
Wind HarVesting

Wind HarVesting on the Home Building Timeline at CC-26

   
Windows DeliVered

Windows DeliVered on the Home Building Timeline at AA-18

   
Windows, Order for DeliVery

Windows, Order for DeliVery on the Home Building Timeline at R-15

   
Wiring, OVerhead

Wiring OVerhead on the Home Building Timeline at I-3

   


 